CLIENT NAME: PROJECTS:
COMPLETED
-
SUMMA KUMAGI, INC. COMPLETE ELECTRICAL PROJECT SUPERVISION, TRINOMA MALL, QUEZON CITY APRIL, 2006
-
MONARK EQUIPMENT CORP. EPC OF 16MW METHANE CO-GENERATION POWER PLANT, MONTALBAN RIZAL OCTOBER, 2008
-
MONARK EQUIPMENT CORP. ENGINEERING DESIGN OF 3MW METHANE CO-GENERATION POWER PLANT, SAN PEDRO LAGUNA
NOVEMBER, 2008
-
SHOCKBLOCK PHILS, INC. COMPLETE ELECTRICAL PROJECT SUPERVISION, 18MW ETHANOL PLANT, ISABELA NOVEMBER, 2012
MAJOR PROJECTS
-
NEW SAN JOSE BUILDER COMPLETE INSTALLATION OF LV BUSDUCT, FORT VICTORIA TOWER 1, 2 & 3, FORT BONIFACIO, TAGUIG
FEBRUARY, 2013
-
REFINERY REPLACEMENT OF 6-UNITS SUBSTATION equipment (BUSDUCT SYSTEM), LIMAY BATAAN
PETRON
APRIL, 2013
-
CARGOHAUS, INC. COMPLETE SUPPLY/ INSTALLATION OF 50KW SOLAR POWER, CLARK PAMPANGA AUGUST, 2014
-
LGC LOGISTICS, INC. COMPLETE SUPPLY/INSTALLATION OF 4MVA POWER TRANSFORMER, HV PANEL, LV PANEL, DISTRIBUTION PANEL, HV CABLE, LV CABLE, LIGHTNING PROTECTION SYSTEM, GROUNDING SYSTEM, AUXILIARY SYSTEM & DATA CENTER, LIMA TECH CENTER-MALVAR BATANGAS
DECEMBER, 2011
-
LGC LOGISTICS, INC. COMPLETE SUPPLY/ INSTALLATION OF 560KW SOLAR POWER, LIMA TECH CENTER-MALVAR BATANGAS
FEBRUARY, 2015
-
MIGHTY CORPORATION COMPLETE INSTALLATION OF LV BUSDUCT SYSTEM, THRU MH-POLY ELECTROMECHS, INC.
MARCH, 2015
-
SOLAR GRID COMPLETE INSTALLATION OF 100KW SOLAR POWER, PAKVITE VALENZUELA CITY
FEBRUARY, 2016
-
MADRAL INDUSTRIAL CORP. COMPLETE INSTALLATION OF LV BUSDUCT SYSTEM, LERATO TOWER TOWER 2, MDC PROJECT
AUGUST, 2016
-
CARGOHAUS, INC. COMPLETE SUPPLY/INSTALLATION ELECTRICAL AT POWERHOUSE INCLUDING POWER CABLE, STAINLESS CABLE TRAY, CIRCUIT BREAKER & METERING SYSTEM
AUGUST, 2017
-
LGC LOGISTICS, INC. COMPLETE SUPPLY/ INSTALLATION OF 60KW SOLAR POWER, CARMELRAY CALAMBA DECEMBER, 2017
ONGOING MAJOR PROJECT:
-
CARGOHAUS, INC. COMPLETE SUPPLY/ INSTALLATION OF ADDITIONAL 60KW SOLAR POWER, CLARK PAMPANGA
-
SUSUMI PHILIPPINES, INC. COMPLETE SUPPLY/INSTALLATION OF UPGRADE SERVICE ENTRANCE AND REPLACEMENT OF POLE MOUNTED TRANSFORMER, FPIP STO. TOMAS BATANGAS
-
MADRAL INDUSTRIAL CORP. COMPLETE INSTALLATION OF LV BUSDUCT SYSTEM, SPRING RESIDENCE TOWER 1, MDC PROJECT, BICUTAN
-
CARGOHAUS, INC. COMPLETE SUPPLY/INSTALLATION OF NEW CIRCUIT BREAKER AT ELECTRICAL ROOM, VETALEZ PARANAQUE
-
LGC LOGISTICS, INC. COMPLETE SUPPLY/ INSTALLATION OF ADDITIONAL STAINLESS CABLE TRAY AT POWERHOUSE (MAIN BUILDING)